Skip to main content
A California garage mid-conversion, its door opening framed out and fitted with a window and a side door

Garage conversion permit timeline

Los Angeles, Seattle, San Francisco, San Diego. Measured from 50,655 public city permit records, not a national average. Updated August 16, 2026.

Your project

San Jose, Sacramento, Oakland do not publish both dates, so their wait cannot be measured.

Printed on the application. Most conversions are an alteration.

Typical wait

Los Angeles · An ADU or JADU · Alteration or repair

109days

Fastest 25%

50d

Typical

109d

Slowest 25%

207d

Slowest 10%

386d

Solid line, typical permit. Dashed line, the 60-day legal deadline. Gold band, the middle half.

7,582 Los Angeles permits. Applications from 2021 to 2024, application date to issue date. Each city uses its own most recent settled years, so the windows differ.

Issued within 60 days of applying

30% were issued inside 60 days of the application going in.

State law sets a 60-day clock, but it starts when the application is deemed complete and pauses when you ask for time. This is your wait, not the city’s compliance.

Share of permits issued within each window
30 days13%
60 days30%
90 days43%
180 days70%
365 days89%

What actually decides it

The review track, not the project. Ask which one yours is on.

Wait by review track
TrackWaitUnder 60d
Plan Check at Countern = 1,898106d32%
Expanded Countern = 9,180112d29%
Regularn = 4,603242d3%

Not in any number above

1 in 5 applications had no issued permit when these records were pulled. 4,471 of 23,735.

These datasets have no withdrawn, cancelled or expired status, so an application with no issue date may be a stalled review or an abandoned project. The records do not distinguish the two, and none of them are marked denied.

Los Angeles, An ADU or JADU. Typical wait 109 days, based on 7,582 permits.

Cities

4

Records used

50,655

Extracted

August 16, 2026

Min sample

30 permits

Deduplicated on permit number, revisions dropped, and a permit only counts when the garage is becoming living space. Cohorts group by the date the application was submitted, never the date it was issued, because grouping by issue date mixes in old backlog and oversamples slow permits. A city only appears when it publishes both dates on the same record. Nothing under 30 records is published. Design, plan preparation, any planning review before the application is submitted, and everything after the permit is issued. Public data from each city, analysed by Renology. Reviewed by Dror Gigi, Co-Founder. Published by JOYOAI LLC. Not legal advice, and not a prediction of any individual permit. Free to cite with a link to therenology.com/tools/permit-timeline.