Permit timeline data: garage-conversion and ADU waits in four cities

An open dataset of 64,427 residential garage-to-ADU and garage-to-habitable-room conversion permit applications in Los Angeles, San Diego, San Francisco, and Seattle, measured from each city's official permit records. Across the 19,848 issued permits in the mature cohorts, the median wait ranges from 69 days in the fastest city to 185 days in the slowest.

Download: aggregates CSV · cohorts CSV · JSON · record-level data + R package · Hugging Face · Version 2026.1 · Retrieved 2026-08-24 · CC BY 4.0

The wait, per city

Issued permits from each city's mature application-year cohorts. Days from application to issuance; within-60 is the share issued within 60 days of applying.

CityPermitsp25Medianp75p90Within 60dCohorts
Los Angeles15,6896914427248422%20212024
San Diego3,1979418535954015%20182021
San Francisco541146921948547%20222025
Seattle4216311218730223%20222025

The review track decides the timeline

Never pool review tracks: a city's tracks can both get faster while the pooled median rises, purely from a mix shift. Cells under 30 records are suppressed and never shown as numbers.

CityReview trackPermitsMedianWithin 60d
Los AngelesPlan Check at Counter1,89810632%
Los AngelesExpanded Counter Plan Check9,18011229%
Los AngelesRegular Plan Check4,6102433%
San DiegoDemolition Permit811567%
San DiegoElectrical-Photovoltaic565557%
San DiegoConstruction Change - Building527140%
San DiegoEncroachment Agreement3711727%
San DiegoAgreement16813226%
San DiegoCombination Building Permit2,30217913%
San DiegoElectrical Permit632938%
San DiegoMechanical Permit623023%
San DiegoPlumbing Permit 613022%
San DiegoBuilding Permit803254%
San DiegoCoastal Development Permit834491%
San Franciscootc alterations permit3733069%
San Franciscoadditions alterations or repairs1662780%
SeattleAddition/Alteration3189927%
SeattleNew981709%

Method

  • Cohorts are formed on the application year, never the issue year. A large share of permits issued in any year were filed earlier, so issue-year grouping oversamples slow permits.
  • Records are deduplicated on the permit number before anything is counted.
  • Review tracks are never pooled into one median.
  • Any aggregate cell under 30 records is suppressed.
  • A city-year enters the aggregates once at least 75 percent of its applications have an outcome.
  • Percentiles are lower-tail order statistics (quantile type 1, no interpolation).
  • The clock excludes: Design, plan preparation, any planning review before the application is submitted, and everything after the permit is issued.

Read this before citing a number

  • The measured wait is the homeowner calendar wait, not a statutory compliance measure. California Government Code 66317 runs its 60-day clock from a completed application and tolls on applicant delay; these records carry only the submission date.
  • An application with no issued date had no issued permit when the records were retrieved. That may be a stalled review or an abandoned project; the records do not distinguish the two, and none are marked denied.
  • Cross-city level comparison is not apples-to-apples; the trend within a city is sound.

Sources

All records come from official city portals, public record, retrieved 2026-08-24: Los Angeles · San Diego · San Francisco · Seattle. No city endorses this preparation. The build script that produced every number is committed in the open repository, and the interactive version lives in the permit timeline explorer.

Cite this data

Ichaki, A. (2026). Residential Garage-Conversion and ADU Permit Timelines for Los Angeles, San Diego, San Francisco, and Seattle. Version 2026.1. Renology. doi:10.5281/zenodo.22079794. https://www.therenology.com/data/permit-timelines

Archived with a DOI on Zenodo, so the citation resolves even if this page moves.