Short answer
If the walls and plumbing stay where they are, a small Austin job can use an Express permit, which the city says it issues in about one business day; Express bathroom permits took a median of 2 days. Plan review takes months: a median of 69 days for a bathroom and 74 for an ADU.
In a Nutshell
- 1 business dayThe city’s turnaround for most Express permitsCity of Austin, Express Permits
- 2 daysTypical wait for an Express bathroom permitCity of Austin permit records, applications November 2024 to October 2025
- 69 daysTypical wait for a bathroom permit that needs plan reviewSame records
- 74 daysTypical wait for an ADU or guest house permitSame records
Renology went through every residential building permit application filed with the City of Austin between November 2024 and October 2025 that was issued by mid-November 2026: 3,081 permits for remodels, additions, ADUs, pools, decks, patio covers, foundation repairs and roofs. New single-family homes are left out. The question we asked is simple: how long did the city take between the application and the issued permit?
The two paths: Express or plan review
Austin sorts small residential work into an Express permit. Everything else goes through plan review, where a city reviewer reads your drawings before the permit is issued. Which path your job lands on decides most of the wait.
- Express covers specific small projects on single-family, duplex and two-family lots: bathroom and kitchen remodels, foundation repair that does not add more than 128 square feet of impervious cover, certain roof repairs and replacements, same-size window replacement, siding, insulation and drywall repair, among others.
- For a bathroom or kitchen, the limits are strict: only the drywall around a tub, shower or sink can come off, walls cannot be moved or removed, and plumbing fixtures cannot be relocated or added.
- The city says it issues most Express permits in one business day, and that the timing can differ in a floodplain or a historic district. Applications are submitted online.
- If the work turns out bigger than Express allows, the city requires a new application with its own fees, and the Express fee is not refunded.
How long each kind of project waits
| Project | Goes Express | Express wait | Plan review wait |
|---|---|---|---|
| Foundation repair (751) | 93% | 2 days | 8 days |
| Kitchen and bathroom together (142) | 29% | 3 days | 45 days |
| Deck (273) | 12% | 6 days | 55 days |
| Kitchen remodel (95) | 25% | too few to say | 58 days |
| Pool or spa (758) | 0% | too few to say | 68 days |
| Bathroom remodel (466) | 55% | 2 days | 69 days |
| Roof replacement (114) | 68% | 1 day | 72 days |
| ADU or guest house (52) | 2% | too few to say | 74 days |
| Patio cover, pergola or outdoor kitchen (283) | 0% | too few to say | 83 days |
| Home addition (147) | 6% | too few to say | 91 days |
Waits are medians from application to issued permit; the number in brackets is how many permits each row is based on. Where fewer than 30 permits took a path, we leave it out rather than guess.
Bathroom remodel
2 days Express, typical wait69 days Plan review, typical waitKitchen and bathroom together
3 days Express, typical wait45 days Plan review, typical waitRoof replacement
1 day Express, typical wait72 days Plan review, typical waitFoundation repair
2 days Express, typical wait8 days Plan review, typical wait
Median days from application to issued permit. City of Austin open data, applications November 2024 to October 2025, issued through November 2026.
Foundation repair is almost always Express: 93 percent of those permits went that way, and the typical wait was 2 days. Roofs are mostly Express too. New structures are the opposite. Pools, patio covers and pergolas almost never qualify, and their typical wait with plan review was 68 and 83 days.
Free contractor matching
Planning a project in Austin?
Pick what you are planning. A coordinator calls within 24 hours and sets up visits from vetted crews who work in Austin. They price the job at your home, so you can compare.
Already have a quote? Check it free before you sign, then compare it with a second crew.
What the wait does not include
- Design and drawings before you apply. For plan-review jobs that is often weeks on its own.
- Time spent answering the reviewer’s comments, if the plans come back with corrections. That sits inside the plan-review wait above, which is part of why it varies so much.
- The work itself and the inspections after the permit is issued.
- Applications that were still waiting in mid-November 2026. The city’s dataset lists issued permits only, so the slowest cases are not in these numbers yet.
How to keep your permit off the slow path
- Decide early whether anything has to move. Keeping walls and plumbing in place is the single biggest time saver on a kitchen or bathroom.
- If plan review is unavoidable, start the drawings before you pick finishes. The permit clock, not the tile, is usually what sets the start date.
- Check whether your lot is in a floodplain or a historic district. The city says those can change the timing even for Express work.
- Hire a crew that pulls permits in Austin regularly. You can look up a contractor’s past permits by address on Austin Build + Connect.
Planning a project in Austin? Compare vetted local crews, free.
Short answers
How long does a bathroom remodel permit take in Austin?
On the Express path, a typical 2 days, and 78 percent came out within a week. With plan review, a typical 69 days, and the slowest one in ten took over 199 days.
How long does an ADU permit take in Austin?
ADUs and guest houses almost always need plan review. The typical wait from application to issued permit was 74 days, and the slowest one in ten took over 300 days.
How long does a pool permit take in Austin?
A typical 68 days with plan review, which nearly every pool goes through. The slowest one in ten took over 247 days.
Do I need a permit to replace my roof in Austin?
The city lists certain roof repairs and replacements among Express permits, and 68 percent of the roof permits in these records went Express, with a typical wait of 1 day. Ask your roofer which applies to your house before work starts.