PREFAB ADU: REQUEST THE SAME SCOPE FROM EACH SUPPLIER Renology planning brief | September 27, 2026 Property / city: Model / size: Quote date / expiry: For each item, record: Included / Excluded / Allowance / Not yet assessed. Name the responsible company and any conditions affecting the price. - Site assessment, survey and required reports - Permit applications, fees and inspection coordination - Foundation and site preparation - Delivery, crane access and installation - Utility routes, connection work and restoration - Selected finishes and appliances - Final inspections and handover - Transport damage, installation defects and product fault contacts Please separate factory production, site work and approvals in the schedule. List work I must arrange separately. Explain how changes are priced and approved. Attach the written warranty terms and the process for reporting a problem. This is a planning checklist, not a contract or an assurance of coverage. https://www.therenology.com/journal/prefab-adu-california-what-companies-charge